The Petäjäskosken 400/220 kV substation

The Petäjäskoski turnkey project was a renewal of 400/220 kV substation owned by Fingrid. Schedule for the project was April 2015 – December 2016. Scope of work:

Extension of 400 kV switchyard, a new power transformer, a new 220 kV GIS switchgear, 220 kV cables, 20 kV reactors, protection and remote control systems and demolition work of 220 kV AIS (Air Insulated Switchgear).


 

Contact us

Here you can send orders or contact us for more information.

First name*
Last name*
Company*
Email*
Phone*
Zip code
City
Message...